• Project Name: Sirhind Canal Crossing, Ropar, Punjab

Nature of Work Lifting of the capsized segments of  bridge and re-launching the bridge of length 134 meters and weighing  480MT

Project Highlight : For the retrieval and re launching of the bridge segment, the client was looking at hiring a super heavy crane whose mobilization and assembly/dismantling time was quite significant. We custom designed a lifting and skidding solution using our hydraulic jacks, skid rollers and push pull cylinders thereby retrieving and positioning the bridge on its final location, safely in a span of few weeks. Besides saving a lot of time for the client, our solution was also quite cost competitive.