We proposed inclined lifting and skidding solution. Since the length of the boiler drum was more than the distance between row columns, therefore, we provided solution to incline the drum at angle of 30 degrees and lift it. To create proper angle for inclination we made structure which included skidding beams and 100 Ton capacity skid rollers .The entire lifting and skidding structure was mounted at an height of 86 m. We lifted the drum from one end to clear the row column by simultaneous skidding of the Strand jack towards the other Strand jack which was kept stationary holding other end of drum. At a height of 70 m, the drum cleared the row columns and thereafter, we made boiler drum horizontal to the ground. After the drum reached the height of 77 m it was skidded 4 m towards the H girders using 100 Ton capacity skid rollers and lowered on to its U’s rods (final position). Considering all safety and quality measures for this heavy lift, we successfully installed the boiler drum to client’s fullest satisfaction.